Dev.IQ · 02

Nine phases. One continuous process.

The land-development lifecycle spans nine connected phases. Bailey leads the planning and civil-engineering work, supports construction, and steps back where responsibility belongs to the developer or builder.

01
Stage 1 — Raw Land
Bailey-led
Stage 1 — Raw Land

Site Identification & Feasibility

Bailey leads the feasibility review: market demand, site identification, zoning and FLUM, utilities, access, constraints, preliminary yield, and the go/no-go decision.

  • Market demand analysis
  • Site identification
  • Zoning & FLUM review
  • Utility availability
  • Access & traffic constraints
  • Environmental & physical constraints
  • Preliminary yield and pro forma
  • Go / No-Go feasibility decision
02
Stage 1 — Raw Land
Outside Bailey's scope
Stage 1 — Raw Land

Land Control

Developer-side phase — Bailey does not participate. PSA or option agreement, due diligence, title and easement review, refined concept and costs, exit strategy.

  • Purchase and Sale Agreement (PSA) or Option
  • Due diligence period
  • Title review and easements
  • Refine concept and costs
  • Exit strategy confirmation
03
Stage 2 — Planning / Concept
Bailey-led
Stage 2 — Planning / Concept

Entitlements (including Preliminary Plat)

Bailey leads the entitlement process from concept planning through the preliminary plat decision. The work combines site information, agency coordination, public meetings, application materials, and the approvals that establish a viable path into engineering design.

  • Concept plan (client approval)
  • Road naming
  • Topo / Survey
  • Pre-application meeting with city
  • Neighborhood meeting
  • Geotech
  • Preliminary plat production
  • Materials & exhibits
  • Legal descriptions
  • Applications
  • Staff report
  • Planning & Zoning Commission recommendation
  • City Council decision
  • Development agreement (if required)
04
Stage 3 — Design / Engineering
Bailey-led
Stage 3 — Design / Engineering

Construction Drawings (CDs)

Engineering design. Bailey produces the civil line work and product fit exhibit, and coordinates the landscape architect (planting plan per code) and surveyor (final plat layout) into one drawing set. Iterative client redlines.

  • Civil line work (grading, utilities, stormwater, streets)
  • Product fit exhibit
  • Landscape plan (landscape architect, coordinated by Bailey)
  • Final plat layout (surveyor, coordinated by Bailey)
  • Client redline rounds
  • Iterative client revisions
05
Stage 3 — Design / Engineering
Bailey-led
Stage 3 — Design / Engineering

Submittal & Approvals (SAs)

Bailey shepherds the submittal package through agency review. Other documents the CDs depend on — legal descriptions and easements from the surveyor, landscape plan from the landscape architect — are coordinated by Bailey into one coherent submittal. Comment-response cycles average two to three rounds. Outcome: CDs stamped and approved.

  • CDs submittal to agencies (irrigation, street, city, fire, health)
  • Permit applications (ITD, 404, etc. if needed)
  • Legal descriptions and easements (from surveyor)
  • Comment-and-response rounds (2–3 average)
  • Stamped and approved plans
  • License agreements
  • Permit issuance
06
Stage 4 — Construction / Recording
Contractor builds, Bailey supports
Stage 4 — Construction / Recording

Construction

Horizontal build — roads, utilities, grading above and below ground. Bailey is not the contractor; Bailey's role is construction observation and agency coordination. Agency inspections and punch list throughout.

  • Construction observation reports (Bailey)
  • Agency inspection coordination (Bailey)
  • Punch list management (Bailey)
  • — On the parcel (contractor): —
  • Clearing, grading, and earthwork
  • Utility installation
  • Road and infrastructure construction
07
Stage 4 — Construction / Recording
Bailey-led
Stage 4 — Construction / Recording

As-Builts / Record Drawings

The surveyor measures what was actually built. Bailey converts those measurements into record drawings, which agencies review for conformity with the approved CDs. The developer may need to remediate punch list items before approval.

  • Surveyor field measurements
  • Bailey produces record drawings
  • Drainage and PI certification
  • Agency conformity review
  • Agency inspection / punch list
  • Approved record drawings
08
Stage 4 — Construction / Recording
Bailey-led
Stage 4 — Construction / Recording

Final Plat Routing & Recording

Bailey prepares the engineering report and final plat applications, then coordinates the surveyor's mylars through agency review, signatures, county recording, and addressing.

  • Engineering report
  • Final plat applications
  • Mylars from surveyor
  • Owner signature
  • Health Department (2–3 weeks)
  • Highway district (3–5 weeks)
  • County Surveyor (2–4 weeks)
  • City (30–45 days)
  • County Plat Review (1–3 days)
  • County Treasurer (1 day)
  • Recorder (1 day)
  • Addressing (3–5 days)
  • Agency inspection / punch list (final round)

Timing note: These durations are planning estimates and vary by agency, jurisdiction, project complexity, and review workload. They reflect typical agency review periods only and do not include Bailey project-management time, preparation between reviews, resubmittals, additional review cycles, permit corrections, or delays caused by incomplete or revised information.

09
Stage 5 — Vertical Development / Sale
Outside Bailey's scope
Stage 5 — Vertical Development / Sale

Vertical Development / Sale

Bailey's engagement ends after Phase 8. The builder or developer handles vertical construction, sales or lease-up, and HOA or asset-management transition.

  • Vertical construction (homes or commercial buildings)
  • Sales or lease-up
  • HOA or asset management transition
Have a project?

The strongest projects start with feasibility.

Bailey can join a project mid-process, but early feasibility creates better context, exposes constraints sooner, and protects the expensive decisions that follow.

Start with feasibility →
Feedback